Pier 6 Replacement
Pier 6 Replacement
Completion Date: 2008-08-14

The work included the complete demolition and disposal of existing piers 4, 6 and 13 and the dredging of approximately 373,000CY of material and disposal in a Confined Aquatic Disposal (CAD) Cell. The new structure is founded on steel pipe piles....

SR 699 Gulf Boulevard Seawall
SR 699 Gulf Boulevard Seawall
Completion Date: 2008-05-16

Work included replacement of approximately 800 linear feet of seawall cap, total replacement of 50 linear feet of seawall, tieback system, associated earthworks, dock tie-ins, and storm water penetration.

Choctaw Point Terminal
Choctaw Point Terminal
Completion Date: 2007-10-30

The work for the new container handling dock structure included the driving of approximately 1,900LF (580m) of sheetpile and combination (Pipe-Z) wall, including 145,562LF of pre-stressed concrete batter piles, and a pile-supported, reinforced...

St. Petersburg Marina Rehabilitation
St. Petersburg Marina Rehabilitation
Completion Date: 2007-05-31

Project entailed the structural rehabilitation of an existing pier, including deck replacement, concrete spall repairs, concrete cap encapsulation, column encapsulation, pile jackets; utility upgrades included electrical, cable, communications,...